Strip-out to handover under one project lead. You get one quote, one schedule, one warranty — not three subcontractors blaming each other when the floor weeps two weeks later.
We don’t move structural walls, we don’t alter electrical circuits ourselves (we bring a Suruhanjaya Tenaga-licensed electrician), and we don’t fit gas heaters without an Energy Commission gas contractor. Everyone we bring is named on the contract.
2.5 to 4 m², fixtures only. Typically 7–9 working days including waterproofing cure.
5 to 7 m², full re-tile, double vanity. 12–16 working days.
Bathroom + laundry yard, partition changes. 18–24 working days.
Cost bands and per-square-metre rates are covered during the site survey — we won’t quote bathrooms blind.